Planned Activities for the Week of 3/28/2022 - 4/3/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Steel Deliveries

  • Steel Erection

  • Prepare and place the 2nd floor slab

  • Prepare and place stem walls on the foundation

  • Concrete deliveries

  • Mechanical/electrical/plumbing rough-in

Weekend Work (3/26): Steel erection.

Note: Concrete deliveries may cause periodic noise and/or vibration. On Tuesday we are planning to place the 2nd floor slab on deck. This activity will start early at 5 a.m. and will go into the evening.

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Concrete placements at the mid-rise

  • MBTA elevator & stair work

  • Steel erection and façade precast install at the tower

  • Steel & deck detailing at the mid-rise

  • Masonry shaft block work at the mid-rise

  • Underground utility work in the mid-rise & tower

  • Site grading at D2.4

Weekend Work (3/26): MBTA elevator work & site clean-up and trash removal operations.

Note: Adjacent to the Allen Street gate, we will continue subgrade work throughout the week which may cause periodic noise and/or vibration.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 4/4/2022 - 4/10/2022

Next
Next

Planned Activities for the Week of 3/21/2022 - 3/27/2022