Planned Activities for the Week of 3/28/2022 - 4/3/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel Deliveries
Steel Erection
Prepare and place the 2nd floor slab
Prepare and place stem walls on the foundation
Concrete deliveries
Mechanical/electrical/plumbing rough-in
Weekend Work (3/26): Steel erection.
Note: Concrete deliveries may cause periodic noise and/or vibration. On Tuesday we are planning to place the 2nd floor slab on deck. This activity will start early at 5 a.m. and will go into the evening.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the mid-rise
MBTA elevator & stair work
Steel erection and façade precast install at the tower
Steel & deck detailing at the mid-rise
Masonry shaft block work at the mid-rise
Underground utility work in the mid-rise & tower
Site grading at D2.4
Weekend Work (3/26): MBTA elevator work & site clean-up and trash removal operations.
Note: Adjacent to the Allen Street gate, we will continue subgrade work throughout the week which may cause periodic noise and/or vibration.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction