Planned Activities for the Week of 1/10/2022 - 1/16/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Form and place pile caps and grade beams

  • Foundation Waterproofing

  • Install temporary electrical service

  • Foundation backfill

Weekend Work (1/8): The project will work Saturday if we loose a day due to bad weather.

Note: Concrete trucks will be in and out throughout the week. 

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Eversource is tentatively scheduled to energize temporary power at Lot 5

  • Concrete placements at the tower composite decks

  • Remaining retaining wall rail install along Milk Alley

  • D2.4 soil export and stormwater storage system install

  • MBTA elevator, bike shelter & temporary trailer work

  • Steel erection and precast plank install at the tower

  • Steel erection and deck detailing at the mid-rise

Weekend Work (1/8): Snow clean-up with-in the site

Note: Soil export and storm water trap install will continue at the D2.4 site, adjacent to the Allen Street gate, Monday - Friday.

Should you have any questions, please reach out to us at info@discoverUSQ.com.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 1/17/2022 - 1/23/2022

Next
Next

Planned Activities for the Week of 1/3/2022 - 1/9/2022