10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Form, reinforce, and place concrete foundation
Strip forms from concrete foundation
Backfill building foundation
Haul in soil for backfill
Install temporary power system and weather enclosure
Weekend Work (1/15): We may need to work the weekend stripping forms and back filling due to weather delays.
Note: Concrete trucks, dump trucks, and excavator are being used through out the week. We are planning to work Monday 1/17/2022.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Eversource is tentatively scheduled to energize temporary power at Lot 5
Concrete placements at the mid-rise podium deck
Masonry at the mid-rise elevator shaft
D2.4 stormwater storage system install
MBTA elevator, bike shelter & temporary trailer work
Steel erection and precast plank install at the tower
Steel erection and deck detailing at the mid-rise
Weekend Work (1/15): The plumber will be setting deck sleeves at the mid-rise podium deck.
Note: Stormwater trap system installation & backfilling work will continue at the D2.4 site, adjacent to the Allen Street gate, Monday - Friday.