Planned Activities for the Week of 1/24/2022 - 1/30/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Remove formwork and haul offsite
Backfill and prepare the site
Install temporary electrical service
Deliver and erect tower crane
Weekend Work. (1/22): We will be erecting the tower crane.
Note: There may be noise due to the crane delivery and installation and backfill and compaction activities.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Eversource is tentatively scheduled to energize temporary power at Lot 5
Concrete placements at the mid-rise podium deck
Masonry at the mid-rise elevator shaft
D2.4 stormwater storage system install
MBTA elevator, bike shelter & temporary trailer work
Steel erection and precast plank install at the tower
Steel erection and deck detailing at the mid-rise
Weekend Work (1/22): Material hoist install and temporary weather enclosure work at the tower.
Note: At D2.4, adjacent to the Allen Street gate backfilling operations will continue Monday through Friday.
Should you have any questions, please reach out to us at info@discoverUSQ.com.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction