10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Remove formwork and haul offsite

  • Backfill and prepare the site

  • Install temporary electrical service

  • Deliver and erect tower crane

Weekend Work. (1/22): We will be erecting the tower crane.

Note: There may be noise due to the crane delivery and installation and backfill and compaction activities.

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Eversource is tentatively scheduled to energize temporary power at Lot 5

  • Concrete placements at the mid-rise podium deck

  • Masonry at the mid-rise elevator shaft

  • D2.4 stormwater storage system install

  • MBTA elevator, bike shelter & temporary trailer work

  • Steel erection and precast plank install at the tower

  • Steel erection and deck detailing at the mid-rise

Weekend Work (1/22): Material hoist install and temporary weather enclosure work at the tower.

Note: At D2.4, adjacent to the Allen Street gate backfilling operations will continue Monday through Friday.

Should you have any questions, please reach out to us at info@discoverUSQ.com.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 1/31/2022 - 2/6/2022

Next
Next

Planned Activities for the Week of 1/17/2022 - 1/23/2022