Planned Activities for the Week of 1/31/2022 - 2/6/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel Deliveries
Steel Erection
Temporary Electrical Installation
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Steel erection & precast plank install at the tower
Steel erection & deck detailing at the mid-rise
Concrete placements at the mid-rise composite decks
Utility underground work at the tower & mid-rise
Masonry CMU block install at the mid-rise.
D2.4 backfill & subgrade work
MBTA elevator, bike shelter & temporary trailer work
Weekend Work (1/29): Snow removal operations
Note: At D2.4, adjacent to the Allen Street gate backfilling and compaction operations will continue Monday through Friday.
Should you have any questions, please reach out to us at info@discoverUSQ.com.
Thank you,