Planned Activities for the Week of 1/31/2022 - 2/6/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Steel Deliveries

  • Steel Erection

  • Temporary Electrical Installation

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Steel erection & precast plank install at the tower

  • Steel erection & deck detailing at the mid-rise

  • Concrete placements at the mid-rise composite decks

  • Utility underground work at the tower & mid-rise

  • Masonry CMU block install at the mid-rise.

  • D2.4 backfill & subgrade work

  • MBTA elevator, bike shelter & temporary trailer work

Weekend Work (1/29): Snow removal operations

Note: At D2.4, adjacent to the Allen Street gate backfilling and compaction operations will continue Monday through Friday. 

Should you have any questions, please reach out to us at info@discoverUSQ.com.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 2/7/2022 - 2/13/2022

Next
Next

Planned Activities for the Week of 1/24/2022 - 1/30/2022