Planned Activities for the Week of 2/21/2022 - 2/27/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Steel Deliveries

  • Steel Erection

Weekend Work (2/19): Steel Erection

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Concrete placements at the mid-rise

  • MBTA elevator, bike shelter & temporary trailer work

  • Steel erection and precast plank install at the tower

  • Steel erection and deck detailing at the mid-rise

  • Masonry shaft block work at the mid-rise

  • Underground utility work in the mid-rise & tower

Weekend Work (2/19): General site clean-up and trash removal at the tower.

Note: Sidewalk subgrade work along Charlestown/MBTA platform may cause periodic noise and/or vibration.

Should you have any questions, please reach out to us at info@discoverUSQ.com.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 2/28/2022 - 3/6/2022

Next
Next

Planned Activities for the Week of 2/14/2022 - 2/20/2022