Planned Activities for the Week of 3/7/2022 - 3/13/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel Deliveries
Steel Erection
Weekend Work (3/5): Steel erection.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the mid-rise
MBTA elevator, bike shelter & temporary trailer work
Steel erection, precast plank & façade precast install at the tower
Deck detailing and wood panel erection at the mid-rise
Masonry shaft block work at the mid-rise
Underground utility work in the mid-rise & tower
Weekend Work (3/5): Trashing out operations at the tower & sidewalk prep along Charlestown & Prospect Street (inside the site limits).
Note: Vibratory work throughout the week along Charlestown for sidewalk & road subgrade work may cause periodic noise and/or vibration.